New Land School
Client
MSA-RA
Area
189,000 ft2
Scope of Work
Complete HVAC, Plumbing, Fire Protection & Electrical design and Top Supervision.
Installed System Details
HVAC : 345 Tons VRF based Central Cooling System.
Plumbing : Water supply and Drainage work.
Electrical : 450 KW Electrical Load & Allied Works.
Fire Fighting : Wet pipe Sprinkler System.
Our Approach And Solution
The expansion includes eight additional wide-body gates, four jet bridge gates and four remote stand operation bus gates to increase capacity in the international terminal. The new restaurants and bars, retail areas, digital art and pet relief area improve the passenger experience. An iconic showpiece within the expansion is an island forest, complete with three live hemlock trees and contained within an open-air glass atrium.