Jawarhat Al Abha
Client
Arabian Centres
Area
472.170 ft2
Scope of Work
Complete HVAC, Plumbing, Fire Protection & Electrical design.
Installed System Details
HVAC : 1950 tons air cooled reversible electric operated screw based central cooling system & Package Units.
Plumbing : Water supply and drainage work.
Electrical : 4.2 MW electrical load & allied works.
Fire Fighting : 500 GPM Sprinkler, Fire Hydrant & FHC System and Fire Extinguishers.
Our Approach And Solution
The expansion includes eight additional wide-body gates, four jet bridge gates and four remote stand operation bus gates to increase capacity in the international terminal. The new restaurants and bars, retail areas, digital art and pet relief area improve the passenger experience. An iconic showpiece within the expansion is an island forest, complete with three live hemlock trees and contained within an open-air glass atrium.